A BUILDING PERMIT IS REQUIRED: For any new construction to include
structural work, additions, patio covers, porches, utility sheds,
roofing, fireplaces, pools, excavations other than building construction,
fences and signs. The homeowner or their agent is responsible for
obtaining a Building Permit when required.
Notice: It is a violation of the code of the Town of Pendleton to
proceed with any construction before an Application for Building
Permit is approved and a Permit has been issued. A payment of double
the fee will be assessed for anyone starting without a permit and
a stop work order will be issued until a Permit is issued.
INSTRUCTIONS FOR APPLYING FOR A BUILDING PERMIT
(this information can be downloaded and printed using the link on
the right in the HIGHLIGHTS box "Building Permit Application ").
• A Building Inspector will assist with filing Building Permit
Pre-application Form and advise of any fees to be paid.
• A plot plan showing the lot and location of buildings on
the property, dimensions to property lines, streets and other buildings,
and the location of the proposed project. A copy of the survey should
be used.
• Drawings must show sufficient information regarding materials
and dimensions. Project must conform to NYS Uniform Fire Prevention
and Building Code. Most projects with structural improvements will
require drawings stamped by a NY State licensed architect or engineer.
The Building Inspector will advise.
• If using a contractor or subcontractors, they must be licensed
in the Town of Pendleton, which requires proof of insurance for
general liability, workers compensation and disability.
• Upon approval of an application, the Building Inspector
will issue a Building Permit and one copy of the approved application
and appropriate drawings. The Building Permit must be posted on
the premises. The permit will be good for twelve (12) months.
• A list of required inspections will accompany the permit.
You must call this office at 716-625-8833 ext. 14 or 15 to arrange
each inspection. You must receive approval from the Building Inspector
after each inspection before continuing with the project.
• Electrical inspections are made bya separate company contractor. Please contact this office for approved contractors by calling 716-625-8833 Ext. 14 or 15; this will require
an additional fee. Inspections will be made prior to covering wires.
• All necessary arrangements for sewer, water and curb cuts
must be arranged with the Public Works Department of the Town of
Pendleton at 625-8033.
• No person shall make any changes to the approved plans before
contacting the Building Inspector.
• Upon notification of completion of all construction and
after an acceptable final inspection the Building Inspector will
issue a Certificate of Occupancy or Certificate of Compliance. It
is unlawful to use any structure in whole or part for any purpose
whatsoever until the certificate has been issued.
Updated 8-14-2009
.
|
|